Wall of Remembrance Build & Memorial Restoration Progress

The names of those who lost their lives during the Korean War — the so-called…

Our Whiting Turner contractors were on site this week to view and test the recently…

PoR PLAZA: A major project milestone was accomplished in the month of April with the…

PoR PLAZA: Sand set paver reinstallation continued for segments 1 & 3 in March. WoR…

Wall of Remembrance – First Panel Unveiling On March 8, 2022 General John Tilelli, Chairman…

PoR PLAZA: Sand set paver reinstallation in segments 3 & 2 are ongoing and will…

PoR PLAZA: Sand set paver reinstallation in segments 3 & 2 are ongoing and will…

PoR PLAZA: Sand set paver reinstallation in segments 3 & 2 are ongoing and will…

November 2021 Onsite Progress PoR PLAZA: Mortar set paver grouting (7’ radius from edge of…

October 2021 Onsite Progress PoR PLAZA: WoR concrete slab: rebar and vapor barrier completed in…

PoR PLAZA: Segment 3 horizontal slab pour was completed on 9/7. WoR concrete slab base…

PoR PLAZA: The leaf collector piping coming out of the pool was completed on 7/19….

PoR PLAZA: The sub-drainage piping and aggregate base installation which began on 5/24 was completed…

PoR PLAZA: Soil removal beneath the demolished slab and cutting and capping of existing utilities,…

CONSTRUCTION BARRICADE: Construction barricades and fencing installation completed this month. Mesh fence with scrim barricade…

CONSTRUCTION BARRICADE: Wooden barricade will be completed by end of week 4/5. Mesh fence with…