The names of those who lost their lives during the Korean War — the so-called “forgotten war” — will never be forgotten again. The Wall of Remembrance is a permanent…

Our Whiting Turner contractors were on site this week to view and test the recently installed lights at the Wall of Remembrance – rail lights along the WOR segment #1,…

PoR PLAZA: A major project milestone was accomplished in the month of April with the completion of the installation of the WoR panels, which completed on 4/9. Sand set paver…

PoR PLAZA: Sand set paver reinstallation continued for segments 1 & 3 in March. WoR panels 001 & 002 were completed on 3/2. Caulking for the WoR panels in segments…

Wall of Remembrance – First Panel Unveiling On March 8, 2022 General John Tilelli, Chairman and President of the Korean War Veterans Memorial Foundation and Ambassador Lee, Soo-hyuck, Republic of…

PoR PLAZA: Sand set paver reinstallation in segments 3 & 2 are ongoing and will continue into March. Segment 1 sand set pavers install picked up on 2/16. The installation…

PoR PLAZA: Sand set paver reinstallation in segments 3 & 2 are ongoing and will continue into February. Segment 1 sand set pavers will begin in February. The installation of…

PoR PLAZA: Sand set paver reinstallation in segments 3 & 2 are ongoing and will continue into January. The last section of the plaza gutter in segment 1 was installed…

November 2021 Onsite Progress PoR PLAZA: Mortar set paver grouting (7’ radius from edge of pool) was completed 11/5. Sand set paver reinstallation (7’ to 32’) began on 11/10 in…

October 2021 Onsite Progress PoR PLAZA: WoR concrete slab: rebar and vapor barrier completed in early October form work is on going and all walls are scheduled to be completed…