PoR PLAZA: Segment 3 horizontal slab pour was completed on 9/7. WoR concrete slab base rebar was started in all segments on 9/14, the pours are scheduled for late October….
PoR PLAZA: The leaf collector piping coming out of the pool was completed on 7/19. Drip line irrigation sleeves began install in segment 1 of the plaza on 7/19. Underground…
PoR PLAZA: The sub-drainage piping and aggregate base installation which began on 5/24 was completed on 6/15. The planting soil in the plaza started on 6/15 and is scheduled to…
PoR PLAZA: Soil removal beneath the demolished slab and cutting and capping of existing utilities, which started in April, both completed on 5/7. Helical pile installation began on 5/10 and…
CONSTRUCTION BARRICADE: Construction barricades and fencing installation completed this month. Mesh fence with scrim barricade was completed on 4/7. The entrance gate was installed and completed on 4/8. Wooden barricades…
CONSTRUCTION BARRICADE: Wooden barricade will be completed by end of week 4/5. Mesh fence with scrim barricade installed with the exception of the construction entrance gate. This entrance gate is…