Memorial Restoration & Wall of Remembrance Build Progress

Korean War Veterans Memorial Foundation Hiring Announcement for Executive Assistant (EA) to the President February…

The names of those who lost their lives during the Korean War — the so-called…

Our Whiting Turner contractors were on site this week to view and test the recently…

PoR PLAZA: A major project milestone was accomplished in the month of April with the…

PoR PLAZA: Sand set paver reinstallation continued for segments 1 & 3 in March. WoR…

Wall of Remembrance – First Panel Unveiling On March 8, 2022 General John Tilelli, Chairman…

PoR PLAZA: Sand set paver reinstallation in segments 3 & 2 are ongoing and will…

PoR PLAZA: Sand set paver reinstallation in segments 3 & 2 are ongoing and will…

PoR PLAZA: Sand set paver reinstallation in segments 3 & 2 are ongoing and will…

November 2021 Onsite Progress PoR PLAZA: Mortar set paver grouting (7’ radius from edge of…

October 2021 Onsite Progress PoR PLAZA: WoR concrete slab: rebar and vapor barrier completed in…

PoR PLAZA: Segment 3 horizontal slab pour was completed on 9/7. WoR concrete slab base…

PoR PLAZA: The leaf collector piping coming out of the pool was completed on 7/19….

PoR PLAZA: The sub-drainage piping and aggregate base installation which began on 5/24 was completed…

PoR PLAZA: Soil removal beneath the demolished slab and cutting and capping of existing utilities,…

CONSTRUCTION BARRICADE: Construction barricades and fencing installation completed this month. Mesh fence with scrim barricade…

CONSTRUCTION BARRICADE: Wooden barricade will be completed by end of week 4/5. Mesh fence with…